Road construction / Construction-accompanying measurement

Object

Achievement time

Principal

Kind of achievement

Construction of local avoidance Kedzierzyn-Kozle with bridge about the Or and connection to DK-40 - section B of km 2+460,00 to km 5+933,41

From August, 2008 to August, 2010

Przedsiebiorstwo Robót Drogowych i Mostowych Spólka Akcyjna (PRDiM)
Kedzierzyn-Kozle

Construction-accompanying measurement
approx. 3.1 km long local avoidance and civil engineering works
Old tacheometry
Mass calculation after across profiles
Final measurement and production of the complete continuance documentation

Construction of the highway A-2 on the segment Knot Stryków II – knot Stryków I as well as planning and construction of the connecting road A-2  and nationalroad No. 14 in the course of A-1

September 2007 to January 2009

Hermann Kirchner Polska Sp. z o.o.
Lódz

Construction-accompanying measurement
of approx. 1.7 km long highway new building and a 2-km-long connecting road
Old tacheometry
Mass calculation after across profiles
Final measurement and production of the complete continuance documentation

New building of the local avoidance Nowa Ruda, street No. 381 on approx. 3 km

April 2007 to August 2008

Heilit + Woerner Budowlana Sp. z o.o.
Wroclaw

Construction-accompanying measurement
of approx. 3070 m long streetbuilding
Old tacheometry
Mass calculation after across profiles
Controlling measurements and supervision measurements
Final measurement and production of  complete continuance documentation

Wroclaw - removal of the Przyjaznistreet between the crossroad to Karkonoskastr. and the settlement Belvedere

August to September 2007

Heilit + Woerner Budowlana Sp. z o.o.
Wroclaw

Construction-accompanying measurement
Mass calculation
Final measurement and production of the complete continuance documentation

engineering buildings

Construction of the local avoidance Kedzierzyn-Kozle with bridge across the Order and connection with the DK 40 - section B of km 2+460,00 to km 5+933,41 - new building 5 bridge building works

August 2008 to August 2010

Bilfinger Berger
Polska S. A.
Warszawa

Construction-accompanying measurement of 5 bridge building works (among other things a bridge about the Or - bridge length 398m)
Planning, realisation and evaluation of working controll and supervision measurements
Final measurement and production of a continuance plan

New building of the local avoidance Nowa Ruda, street No. 381 on approx. 3 km - new building 7 bridge building works

April 2007 to August 2008

Heilit + Woerner Budowlana Sp. z o.o.
Wroclaw

First  measurement
Construction-accompanying measurement of 7 bridge building works, planning, realisation and evaluation from working controll and
Supervision measurements
Final measurement and production of a continuance plan

11 bridge building works
Removal highway A 18 Królów – Zary (approx. 15 km)

December 2004 to March 2007

Joint Venture „BÖGL-BERGER, Sub-Section II”
Sengenthal

Realisation and evaluation of working controll and supervision measurements in 11 buildings

Mass inquiry / Mass comparison

Building of highway A4 and express-road S69 with Rzeszów

October 2009

ALPINE Bau GmbH
Salzburg

Examination of the old area data on
approx. 9.0 km

Building of express-road S-69 Bielsko-Biala - Zywiec

September to Oktober 2009

ALPINE Bau GmbH
Salzburg

Examination of the old area data on approx. 15.0 km

Wroclaw, new building express-road S-8 Wroclaw - Syców km 0+500 - km 22+593,31

September 2009

ALPINE Bau GmbH
Leipzig

Mass calculation earth construction on approx. 22.0 km, examination of the old area data

building of express-road S 5 Gniezno – Poznan, Odcinek I i Odcinek II

August 2009

Bunte Polska Sp. z o.o.
Warszawa

Mass calculation earth construction on approx. 18.8 km
after across profiles

building of express-road S8 Wroclaw – Syców from km 29+800 to km 54+910

August 2009

ALPINE Bau GmbH
Leipzig

Mass calculation earth construction on approx. 25.1 km, examination of the old area data

Droga Ekspresowa Nr 8 and Droga Krajowa Nr 63 near Zambrów - Mass examination

July 2009

Bunte Polska Sp. z o.o.
Warszawa

Mass calculation earth construction on approx. 16.0 km
after across profiles, mass distribution

Highway A 2 Lódz – Warszawa, km 394+300 bis 431+500 –
Mass examination

July 2009

Bunte Polska Sp. z o.o.
Warszawa

Mass calculation earth construction on approx. 37.2 km
after across profiles, mass distribution

structural engineering

Pietrzykowice
„Servicestation for Volvo trucks”

July 2008 - January 2009

Martifer Konstrukcje
Sp. z o. o.
Gliwice

Developing and actualisation of the map for project purposes, old tacheometry before start of construction work and earth mass inquiry
marking out of the building axes, drainage facilities, public thoroughfares, Krahnbahn, evenness check, controlling measurements,
Final measurement incl. production of the documents for the land survey office

 building of working hall„Michael Bubolz Sp. z o.o.” in Siechnice

July 2007 - June 2008

Stahlbau Stieblich Budowa Hal-Biuro Projektowe Sp. z o.o.
Walce

Production and actualisation of the map for project purposes, old tacheometry before start of construction work and earth mass inquiry
marking out of the building axes, drainage facilities, public thoroughfares
Final measurement incl. production of the documents for the land survey office

Swidnica - building factory building of the Fa. Krause

May 2006 to the mittle of 2007

Bickardt Bau Polska
Sp. z o.o.
Wroclaw

Measurement-technical tacheometry, mass calculation

Draught measurement / Final measurement

Torun, commercial training centre and official training centre "Zieleniec"

December 2007 - January 2008

PROJEKTBAU Sp. z o.o.
Boleslawiec

Construction of the map for project purposes, tracing achievements

Wroclaw, ul. Powstanców Slaskich

June 2007

„BIPROSKIM“ Sp. z.o.o.
Wroclaw

Construction of the map for project purposes

building of express-road S-8, km 0+000km do 22+564 with Olesnica

November to December 2006

Przedsiebiorstwo Geodezyjno-Inzynieryjne
WiM Spólka z o.o.
Wroclaw

Preparation of the documentation for the land survey office, complementary final measurement on approx. 22.6 km

Building admissions / rent surfaces

Wroclaw, Pasaz pod Blekitnym Sloncem, Rynek
Quattro Forum, ul. Legnicka

May to July 2009

Knight Frank Sp. z o.o.
Wroclaw

Building dimension to the surface regulation after the norm PN ISO 9836:1997,
approx. 7,800 m ˛

Wroclaw, ul. Szwedzka – office
 „get six“

Dezember 2008

get six Sp. z o.o.
Wroclaw

Local dimension and calculation of the rent surfaces to Vorschift of the renter, approx. 600 m ˛

hydraulic engineering

Sw. Katarzyna and Olawa – rebuilding and modernisation of the riverbed of the Olawa

July to August 2009

Dolnoslaski Zarzad Melioracji i Urzadzen Wodnych we Wroclawiu
Wroclaw

measurement of the river axis on approx. 9.5 km, creation of 40 height fixed points

other

Airfields to North Polland –  development of the airfields Zegrze Pomorskie, Debrzno and Slupsk

2006 and 2007

GEO-METRIK- Ingenieur- company mbH Rhein-Main

Regulation of passport points for the production of plans on the basis of aerial pictures, creation of fixed points

Wind - services for the establishment of  arrangements for windenergy

Establishment of wind energy arrangements in Poland October 2008 to July 2010 Polish energy supply enterprise

Draught measurement and construction measurement,
Documentation (continuance documentation) of the entrance ways as a photo and videodokumentation of the  entrance way,
Implementation planning of the entrance ways, stand areas and excavation pits,
Driving simulation of the critical points,
Mass inquiry and surface inquiry as a basis for the account,

Production purchase of land plans

 